Hawkins New Business Manager – North, Olivia Pearson, says achieving sustainability wins at the very start of a project comes down to better planning, and involving builders and subcontractors early enough that their experience shapes the design, not just the delivery.
Projects championing new green building materials or lower-carbon construction methods dominate headlines about sustainability. But the biggest wins aren’t coming from what we build with — they’re coming from how well we plan before we build at all.
These gains happen before the first shovel breaks ground, and their potential to reduce waste and drop carbon emissions surpasses almost any other single action.
Overseas research from the US Construction Industry Institute estimates rework costs at around 5% of a project’s value. In my 25 years in the industry, I’ve seen other companies’ projects sent back to the drawing board mid-construction — that’s waste no amount of smart materials selection can compensate for.
Achieving sustainability wins at the very start of a project comes down to better planning, and involving builders and subcontractors early enough that their experience shapes the design, not just the delivery.
Modern Building Information Modelling (BIM) platforms make that collaboration far easier to achieve, letting multiple parties plan and sequence construction before a dollar is committed to site.
That’s borne out by research published in the Ain Shams Engineering Journal in 2025, which modelled the impact of BIM-based design coordination on a sample project and found it led to a 15% reduction in embodied carbon, along with a 10% decrease in cost.
At Hawkins, using Revizto’s collaboration hub is business-as-usual across every project we run, from commercial towers to airports, universities and hospitals.
Some of the projects we work on can generate as many as 12,000 A3 PDF drawings. Managing that digitally rather than in print isn’t just a massive paper saving — it also means field teams are always working from the current version.
Since the start of June, we’ve had more than 300 unique users on the platform — more than 200 of them from external clients and subcontractors — generating 8966 interactions. At a conservative five minutes saved per interaction, that’s 747 hours saved, or 249 hours a month.
We’re also extending our use of BIM into 4D modelling, incorporating construction sequencing to help us manage the tens of thousands of seismic restraints some projects require. Getting that right in the model avoids a huge amount of on-site rework. And that’s where the sustainability gains add up.
Better planning isn’t just good business — it’s one of the biggest sustainability levers our industry possesses.